Despite the soaring temperatures, there’s no slowing down at Birling! Katie, Kate, and Diane from our sales team recently joined Senior Project Manager Wes and were chaperoned by TRN’s Project Manager and HSEQ Officer, for an exclusive on-site update.
The team witnessed firsthand the remarkable progress being made, setting the stage for a vibrant and connected community.
Katie’s Highlights
Katie, our Sales Manager, shared her excitement:
“Seeing the wide roads taking shape, especially compared to other communities in the area, the well-placed roundabout at the heart of the development, and the progress on infrastructure like pipework and dam filling—it’s all coming together beautifully. I’m particularly thrilled about how easily future residents will walk from the retail space to the Homestead and hero park. It’s a community that’s built for connection and quality living!”
On the Ground Progress
- Pipes & Storm water: Approximately 800 meters of storm water infrastructure has already been installed, ensuring readiness for stages 1, 2, and 5.
- Wastewater Infrastructure: Preparations are well underway, pending Sydney Water imminent approval.
- Stage 1 Developments:
- Bulk earthworks are nearly complete.
- Lime stabilization has been applied, and a protective sandstone layer will soon follow.
- Services like storm water, electrical, telecommunications, water, and sewer connections are next on the agenda.
- Retaining Walls: Approved for construction, with final colour choices being made alongside the landscape architect.
- Woodland Park 1: Design plans are being fine-tuned to integrate preserved trees into the park layout.
A Vision for Connectivity and Safety
The roundabout at Birling’s entry is designed to offer free-flowing traffic while serving as a landmark feature with potential for striking landscaping. Meanwhile, road density testing and traffic signal approvals are paving the way for seamless movement across the community.
A Well-Resourced Operation
With 25-30 workers currently on-site, and capacity for up to 360 staff and 400 pieces of equipment, the scale of work underway is truly impressive.
As construction progresses, we’re thrilled to see Birling’s vision coming to life—setting the foundation for a vibrant, family-friendly community. Stay tuned for more updates, and thank you for being part of this exciting journey!
🎥 Watch the short video of the team’s visit to see the action firsthand!